Hasketon Road in Woodbridge shuts round the clock from 23 November to 16 December while a new zebra crossing is built. Comments close on 25 November.
Hasketon Road in Woodbridge will be closed 24 hours a day from Monday 23 November to Wednesday 16 December. Suffolk County Council is building a new zebra crossing there. It is one of the crossings promised under the £5 million Active Travel Woodbridge scheme.
The dates are on the county’s ongoing improvement schemes page. The road is closed in both directions, with a signed diversion via Grundisburgh Road and the A12.
What happens and when
The county lists two phases:
| Phase | Dates | Hours | Diversion |
|---|---|---|---|
| 1: new zebra crossing | Mon 23 Nov to Wed 16 Dec | 24 hours, both directions | Grundisburgh Road and the A12 |
| 2: resurfacing and new road markings | Thu 17 Dec to Sat 19 Dec | 7pm to 5am | Through the town centre (see below) |
For the three overnight closures in December, the diversion changes. From the town end, traffic goes from Burkitt Road via:
- Theatre Street and New Street
- St Johns Street and the Thoroughfare
- Melton Road and Woods Lane
- the A12, and back on to Hasketon Road
From the A12 end, it runs via Ipswich Road, Station Road, Quay Street, Church Street and Theatre Street.
The county says access will be kept for people living inside the closure “when possible”. Live updates are on the one.network roadworks map under scheme number 15620.
Where the crossing goes
A separate county notice, published on 4 November, sets out the no-waiting zone that every zebra crossing needs. It puts the centre of the crossing on Hasketon Road 24.7 metres south of its junction with Catherine Road. The zig-zag controlled area would run for 41.6 metres on both sides of the road.
The scheme page itself names only “Hasketon Road, Woodbridge”. It does not say how much of the road will be shut while the crossing is built.
Promised for early 2026
The crossing is late. When the county finished the first Active Travel Woodbridge crossing, on Burkitt Road outside St Mary’s Church of England Primary School, it said two more would follow. Its news release of 10 September 2025 said crossings at Hasketon Road and Grundisburgh Road were “scheduled to be completed in early 2026”.
We have found no dates for the Grundisburgh Road crossing. The wider scheme, including a town-wide 20mph limit, is due by early 2027. Background: Woodbridge 20mph limit by early 2027.
Have your say on the crossing
The 4 November notice is a proposal, so it can still be commented on. Write to Suffolk County Council Legal Services, Endeavour House, 8 Russell Road, Ipswich IP1 2BX, or email highwayslegal@suffolk.gov.uk, by Wednesday 25 November. You can ask the council for a map of the crossing and its reasons for proposing it.
Also in Woodbridge the week before
From Monday 16 to Friday 20 November, 8am to 5pm, the county is sealing footways on three roads, one at a time. Each is closed while the work is done:
- Cherry Tree Road, with a diversion via Ipswich Road and Kingston Farm Road
- Kingston Road, via Cherry Tree Road and Ipswich Road
- Westholme Close, with no diversion
The county’s closure notice of 5 November names the second road as Kingston Farm Road, while its scheme page says Kingston Road. Watch for the signs.
What it means for you
- If you drive Hasketon Road to reach the A12, use Grundisburgh Road from 23 November to 16 December.
- If you live on the road, expect access to be kept where possible, but allow for short delays while work is under way.
- If you walk along Hasketon Road, the county’s dates have the crossing built by 16 December and the road markings done by 19 December.
- If you want to comment on the crossing’s position or the parking it removes, do it by 25 November.
Every closure in and around Woodbridge is on our roadworks and travel page, updated on each visit.