Sizewell C's Westleton traffic calming starts on 2 November, with closures to 24 December. Parishes say B1125 traffic is up 45%; Sizewell C says it is within forecast.
Work on the long-promised Sizewell C traffic calming scheme in Westleton starts on Monday 2 November. It comes as villagers along the B1125 say the road has become a short cut for traffic heading to the construction site.
The works run until 24 December, with temporary traffic lights and a series of short closures in the village. A separate water mains job shuts the B1125 Reckford Road, between Westleton and Middleton, from 9 November until March.
Westleton is about five miles north of Saxmundham. The B1125 runs from the A12 at Blythburgh south through Westleton and Middleton to the B1122, the main road into Leiston and the Sizewell C site.
What closes, and when
Westleton Parish Council’s summary, published on 16 October, and the closure orders give these dates:
| Road | Closed | Times |
|---|---|---|
| Mill Street, 40 metres from the B1125 | 2 to 14 November | All day |
| B1125 Reckford Road, bottle-bank lay-by to the Middleton junction | 9 November to March 2027 | All day, residents’ access kept |
| The Hill, 80 metres from Blythburgh Road | 9 to 25 November | Weekdays, 7am to 5pm |
| Yoxford Road, the cut-through from Reckford Road | 10 to 25 November | Weekdays, 7am to 5pm |
| The Street (B1125) and Reckford Road | 14 to 24 December | Overnight, to 5am |
The closure orders for Mill Street, The Hill and Yoxford Road were published by Sizewell C in October. The Mill Street diversion uses Bakers Lane and the B1125.
The overnight December closures are for removing and repainting white lines. The parish council’s summary says they run from 8pm. The One Network listing, quoted in the parish council’s October minutes, gives 7pm. Either way, the parish says the noisiest work will be finished by 11pm. Residents can reach their homes by speaking to the contractors.
The Reckford Road closure is for Essex and Suffolk Water main replacement. The parish council says the road will reopen for two weeks over Christmas. The county council’s order gives the dates as 9 November to 22 December, then 4 January to 1 March 2027, for 1,400 metres north from Rectory Road. It diverts traffic via the A12 and the B1122.
What the scheme includes
The scheme goes back to a village consultation in May 2024. Residents backed average speed cameras unanimously, and Sizewell C’s operator and the councils agreed to install them at a B1125 Working Group meeting on 11 June 2024.
The parish council’s report of that meeting says residents supported:
- white fencing on the verge at each end of the village on the B1125
- a one-way system around the Argyll House traffic island
- an island with three parking bays in front of the church entrance
- more parking by the Village Hall
- the proposed double yellow lines
- a hard build-out for the crossing to the playing field
Residents rejected a raised road in the middle of the village, coloured road surfaces and three pedestrian crossings.
The same report said the cameras and measures would go in during the first half of 2025. In February 2026, the Northern Transport Forum was told the work had slipped to spring 2026. The reason given was delay to improvements on the B1387, the link road from the A12 at Blythburgh. It is now starting in November.
Why villagers are angry
Seven parish councils and four district councillors wrote to Sizewell C, Suffolk County Council and Suffolk Constabulary on 5 February 2026. They said peak-hour traffic on the B1125 had risen since construction began. They also said residents had reported “dangerous, fast driving”.
The signatories were the parish councils of Blythburgh, Darsham, Middleton, Theberton and Eastbridge, Walberswick and Westleton, plus Dunwich Parish Meeting.
The letter describes a road with deep gullies at the verges, frequent flooding, mud from field exits and no white lines in places. It singles out a junction known locally as the “5 fingers”. It asked for:
- a 40mph limit from the A12/B1387 junction to the northern edge of Westleton
- a 30mph limit from Westleton to the end of the B1125 south of Middleton
- traffic calming in Middleton, which was not part of the original working group
- Sizewell C to track its own and its contractors’ vans and 4x4s, as it does its lorries, and keep them off the B1125
- modelling of how the new roads will change traffic on local B roads
In March, the chair of Westleton Parish Council, Andrew Turner, gave the figure at the heart of the dispute. Speaking at a Sea Link planning hearing on 24 March, he said the B1125 was “suffering a 45% increase in traffic volume and high traffic speeds during peak hours because of Sizewell C traffic”. He said HGV tipper trucks had begun to use it too.
What Sizewell C says
Sizewell C’s chief executive, Nigel Cann, replied on 9 February. He said its monitoring showed B1125 volumes “remain within the forecast ranges assessed during the planning process”. Based on a survey in October 2025, he said there was “no evidence at this stage of a material increase attributable to Sizewell C construction traffic”.
The letter promised further surveys in April and a permanent traffic counter on the B1125. It said decisions on speed limits, traffic calming and enforcement “sit with” the county council and the police, not Sizewell C.
The two positions have not been reconciled in any published document we could find. We have not seen the results of the April survey.
The park and ride is meant to fix it
Both sides point to the Northern Park and Ride at Darsham as the answer. The parishes’ own letter accepts that B1125 traffic “should decrease” once it is fully running.
Sizewell C opened the first section in late 2025, with space for up to 1,250 vehicles when complete. It said then that the site would be fully operational by summer 2026. In February, the transport forum was told full use was expected in late October.
We could not confirm today whether it has reached full capacity. The Sizewell Link Road, the new route from the A12 to Leiston, is due to be finished in the third quarter of 2027, according to the February forum notes.
District councillor Paul Ashton is also still pressing for the B1125 to be closed off at Blythburgh, September’s parish minutes record. Walberswick is hesitant until junction work on the A12 is done.
What it means for you
- If you drive through Westleton: expect temporary lights from Monday, and allow extra time until 24 December.
- If you use Reckford Road towards Middleton: it shuts from 9 November. Use the A12 and the B1122 instead. The road should reopen for two weeks at Christmas.
- If you live on a road being worked on: the parish council says Sizewell C will write to every resident, and contractors will speak to anyone whose parking is affected. Enquiries go to the Sizewell C Information Office, 48-50 High Street, Leiston, or info@sizewellc.com.
- Night drivers in mid-December: The Street shuts overnight from 14 to 24 December.
Every closure in the area this week is on our roadworks and travel page. For the earlier A12 night closures at Darsham, see our report.
Have your say