Ministers approved Sea Link on 30 October: a 26m converter station near Saxmundham and a landfall between Aldeburgh and Thorpeness. Challenges close 11 December.

The government has approved Sea Link, National Grid’s undersea power cable from the Suffolk coast to Kent. Minister Curran made the decision on Friday 30 October, for the Secretary of State for Energy Security and Net Zero. East Suffolk Council had objected throughout.

The decision letter says the need for the link outweighs the harm. It also accepts that some of that harm, to the landscape around Saxmundham and Friston, will last beyond 15 years.

What gets built in Suffolk

The Planning Inspectorate’s project page carries the letter, the order and the inspectors’ report. The Suffolk part of the scheme is:

  • a new substation near Friston, now called Kiln Lane Substation
  • a 2 gigawatt converter station near Saxmundham
  • about 1.9 km of underground cable between the substation and the converter station
  • about 10 km of underground cable from the converter station towards the coast
  • a landfall on the beach between Aldeburgh and Thorpeness, with the joint bay about 900 metres inland

From there the cable runs about 122 km under the sea to Pegwell Bay in Kent.

The order itself caps the buildings. The converter station near Saxmundham can stand 26 metres above existing ground, not counting roof equipment. The Kiln Lane substation can stand 16 metres above a finished ground level of 18.5 metres above sea level.

National Grid has five years from the date of the order to start work.

What the government accepted it will cost the area

The minister agreed with the inspectors’ weighting of each harm. The heaviest on the Suffolk side are:

  • landscape and views: “great negative weight”, with significant effects in Suffolk lasting more than 15 years after building finishes
  • farmland: “moderate negative weight”, for the permanent loss of 10.91 hectares of the best farmland in Suffolk under the substation and converter station
  • heritage: “moderate negative weight”, with less than substantial harm to the setting of Hurts Hall, Hill Farmhouse, St Mary’s Church in Friston and the Saxmundham Conservation Area
  • wildlife: “moderate negative weight”, for habitat lost during building

The letter also finds a “significant cumulative level of harm” to the Suffolk Coast National Landscape while construction runs alongside other projects. National Grid will pay into a compensation fund for the National Landscape to offset part of it.

On traffic, the government found no significant effect, but accepted that traffic and lorries will cause “some driver delay”. Heavy loads for the Saxmundham site are planned to use the B1121 over the Benhall railway bridge, which carries a 46-tonne limit. The letter says a survey of the bridge has still not been completed; National Grid sent its plan for it to Suffolk County Council on 1 September.

The inspectors received 6,061 written representations. More than 2,220 argued that alternatives had not been properly looked at, and more than 1,300 asked why brownfield sites were not used.

What the council said

East Suffolk Council said it was disappointed. It objected at every stage.

Cllr Tom Daly, the cabinet member for energy projects, said: “We are hugely concerned that the Sea Link project will result in yet further unacceptable harm to the communities, environment and economy of East Suffolk over and above the other existing and proposed infrastructure projects being forced upon our local communities.”

The council says it is still reading the order and will now work with National Grid “to secure the best possible outcomes”.

What it means for you

  • There is no appeal, only a court challenge. A claim for judicial review must reach the Planning Court within six weeks starting the day after the decision was published. That runs to Friday 11 December.
  • If you own land on the route, the order grants National Grid compulsory purchase and temporary possession powers. The letter lists Aldeburgh Golf Club among the landowners who had not reached agreement.
  • The building designs are not final. The converter station and substation cannot be built until their design, scale and appearance are approved by the discharging authority, after review by an independent design panel.
  • Questions about the decision go to the Department for Energy Security and Net Zero at energyinfrastructureplanning@energysecurity.gov.uk. National Grid’s Sea Link line is 0808 134 9569.

The same stretch of coast already carries Sizewell C’s road works, and National Grid Ventures’ LionLink converter station is also proposed in Suffolk. The letter says National Grid planned a design workshop with LionLink in late September.